12 workers can do a peice of work in 20 days. How many workers should be added to complete work in 16 days?​

Respuesta :

atchleyamirah69
atchleyamirah69 atchleyamirah69
  • 01-04-2021
3 workers

if 12 workers can do a piece of work in 20 days, then one person can do it in 240 days. 240/16 is 15. That is the number of workers that you need in total to it in 16 days. Since the question ask how many more workers,
15 - 12 = 3 more workers.
Answer Link

Otras preguntas

why are baboons, sparrows, and human beings considered both primary and higher order consumers?
HELP PLEASE!!! Solve for u:9/11u−1=5/6 answer options u=121/54 u=1/54 u=−11/54 u=−1/66
mi hermano juega al tenis
Simone applied the distributive property using the greatest common factor to determine the expression that is equivalent to 24 + 56. Her work is shown below. Fa
After ringing up the sale at a retail store, all but one item is ready for the customer. it may take 5 minutes before the item is ready. the employee should:
10. Which change to a DNA molecule would have the least effect on an organism?
PLEASE HELP!!! like ASAP!!! A. X= 4B. X=-16C.X=16D.X=-4
What applies to the collision therory
Based is scientific research what best describes mutation
Triangle ABC has vertices at A(–2, 3), B(–3, –6), and C(2, –1). Is triangle ABC a right triangle? If so, which angle is the right angle?