  • 14-02-2021
  • Mathematics
contestada

It will take 48 hours of work to complete the garden.
The garden must be finished in 3 days.
Each gardener works for 8 hours per day.
How many gardeners are needed?

Respuesta :

courtneytalley1 courtneytalley1
  • 14-02-2021
6 Gardner’s because 48/8=6
Answer Link

Otras preguntas

As president of the Student Council for two years now, I think that it is time we try to establish a better system for spending our funds. What kind of appeal
What type of consumer is a python?
How many Days a week, at most, could combat take place?
an object moves in uniform circular motion what is true regarding the force on the object
Sentence with unblock
what is the greastest factor of 23 and 46
choose a substance you're familiar with. what are its physical and chemical properties? How would you measure its density? What are some physical and chemical c
Which word is the superlative form? farther weakest less more impressive
What made you decide for Leila and Geo’s costumes?
What is the function of each of the three main parts of a seed? How do they work together to produce a new plant?