It takes 20 men 60 days to complete a building work.How many days longer will It take 15 men, assuming they work all work at the same rate?

Respuesta :

maempress
maempress maempress
  • 13-07-2020

Answer:

80days

Step-by-step explanation:

20m=60days

15m(will take more days)

20÷15×60 = 80 days

Answer Link

Otras preguntas

A combined total of $46,000 is invested in two bonds that pay 4% and 9.5% simple interest. The annual interest is $3,490.00. How much is invested in each bo
I Am A Number That Is Double The Product Of 2 And 7. One Of My Factors Is 7 What Is My Other factor
what is 33 1/2 of 24 and 37 1/2 of 80 and finally, what is 66 2/3 of 45
What is 7% tax on a $9.79 purchase
A combined total of $46,000 is invested in two bonds that pay 4% and 9.5% simple interest. The annual interest is $3,490.00. How much is invested in each bo
What does ayudando mean?
Explain the transition from the Roman society to medieval society. Politically, Socially, Religiously, and economically. How did this thing change Rome to a med
How many quarts are in 2 and 3/4 of a gallon
what is 33 1/2 of 24 and 37 1/2 of 80 and finally, what is 66 2/3 of 45
what is 2.5 % of 16 ?