If you want to give a vendor an incentive to complete work early, which type of contract would you use?


Respuesta :

leiraallen
leiraallen leiraallen
  • 16-05-2020

fixed price contract: The vendor will be paid a fixed payment regardless his time spending. Thus the vendor will try to complete work as soon as possible, then he can receive his payment/ incentive for completed work

Answer Link

Otras preguntas

Which of these helps you understand what people are saying to you? A. Thinking about how you'll respond B. Looking away while they're speaking C. Thinking about
julia is weighing several mineral samples for science class. Which unit of measure could she use to record her measurements.
Which of the following is the most accurate description of the Nazi camp built at Auschwitz, Poland?
Which lines from Book 13 of Homer's Odyssey depict the theme of disguise?
Which situation is considered reinforcement
What happend on summer 1943? 2. World war
A housekeeper would most likely fall under this classification
Weather satellites are usually placed on: north-south orbits east-west orbits oblique orbits synchronous orbits
What statement best summarizes the plot of the Divine Comedy?
Drugs are substances that cause a change in a person's physical but not mental state.True or Flase