It takes 3600 person hours to complete a project. How many weeks will it take a team of 15 people to complete the job if each person works 8 hours, 5 days a week

Respuesta :

Llowrance1
Llowrance1 Llowrance1
  • 15-03-2020

Answer:

6 weeks

Step-by-step explanation:

x = # of weeks

15 times 8 times 5 = 1 week,

so 15 times 8 times 5 times x = 3600 is the equation

Solve for x to get x = 6

Answer Link

Otras preguntas

1. Name two elements that go through alpha decay
what is1250 divided by 3
Write the equation in slope-intercept form. 2/3(6y+9)=3/5(15x-20)
What was the purpose of the Open Door Policy?
I have to solve for b but I can't figure it out
Which expressions represent the distance between the two points? Choose all answers that are correct. The number line shows two points with coordinates negati
If an element has more than one ionic charge, how is that piece of information represented in a chemical name?
what is an orginasim that feeds off of a living host?
When changes occur in a DNA sequence, _______ produced from the DNA may not function correctly, and a _______ disease may result. A.proteins, genetic B.carbohyd
if a square has an area of 225 square feet what is the length of each side