If it takes 6 men 4 days to dig a hole 3 metres deep, how long will it take
10 men to dig a hole 7 metres deep?​

Respuesta :

Аноним Аноним
  • 15-06-2019

Answer:

I think the picture here explains you everything

hope this helped

Ver imagen Аноним
Answer Link
jasminreveles000 jasminreveles000
  • 25-02-2021

Answer:

8 days

Step-by-step explanation:

Answer Link

Otras preguntas

Though unemployment during the Great Depression was widespread, it was higher in some parts of the United States than in others. How might a microhistorian and
The ratio of the number of people who own a smartphone to the number of people who own a flip phone is 4:3. If 500 more people own a smartphone than a flip pho
The Patels took out a 15-year mortgage. How many monthly payments will they have to make on this mortgage?
Why is every prime number greater than 2 an odd number?
45/60 in simplest form
Which greeting uses commas correctly? a. Dear, Uncle Doug, b. Dear, Uncle Doug c. Dear Uncle Doug, d. Dear Uncle, Doug,
Which of the following proportions are true 1:4= 2:5 6:9= 10:12 5:11= 15:30 2:7= 4:14
what is 1,722 divided by 13
How are the gold medal and the human cell similar
Describe some ways the environment shaped ancient Egyptian culture?