Consider the following project
Activity’s Name Immediate predecessor Time to complete the job
A 3
B 2
C B 4
D C 3
E A, C 1
F D, E 1
1. Draw a network diagram representing this project.
2. Identify the critical path.
3. What is the minimum time needed to complete this project​

Respuesta :

Otras preguntas

Tasha believes that she can rewrite the difference 120 - 36 as a product of the GCF of the 2 numbers and another difference. Is she correct?
how to solve x to the power of 2 = 14
what are some fun facts on animal and plant cells.
If Olivia and Shawn have another child, which of the following genotypes is possible for the child? A. Mm only B. MM only C. MM or mm only D. MM, Mm, or mm
What conditions must be met in order for a reaction to be considered exothermic?
Explain the connection, or relationship between a protagonist and an antagonist.
a couple wants to install a square mirror that has an area of 500 square inches.to the nearest tenth of an inch,what length of wood trim is needed to go aroun
The most commonly spoken language in the Fertile Crescent around the time of Jesus was
1/3(9x+27)-4=1/2(2x+54)
The most commonly spoken language in the Fertile Crescent around the time of Jesus was