buhlecatday5536 buhlecatday5536
  • 15-02-2024
  • Computers and Technology
contestada

Activity D on a CPM network has predecessors B and C and has a successor F. D has a duration of 6. B's earliest finish is 18, while C's is 20. F's late start is 26. Which of the following statements is true?
a. D is the critical path
b. D's late start is 26
c. D's earliest start is 12
d. D's latest finish is 20

Respuesta :

Otras preguntas

Most of the mass of an atom comes from the (blank) and (blank)
The plains Indians embraced the ghost dance movement because they were?
If a carbon atom is bonded to two hydrogen atoms and two carbon atoms, what type of bond must exist between the carbon atoms?
please answer in fractions not decimals and show your work -8 = 7a - 11
The market where 4 sell goods and services to households and the government is called the A. goods market B. factor market C. capital market D. money market
what is 0.00666 as a percent
there are 2 pieces of licorese and 3 people how do u get every one a equal amount
What is the independent and dependent variable for a dry ice experiment
What are these closer to 1/2,0,or 1: 5/6 7/13 3/5
What are these closer to 1/2,0,or 1: 5/6 7/13 3/5